Fall 2017

Fall 2017  -  Meet with BIMPRD (Parks) staff to review conceptual alignment of 820’ trail along the ROW. Parks is concerned about removing trees along the ROW that currently serve as a backdrop for views in the park across the pond. Sakai Park designers (Jones & Jones) propose a 12’ wide boardwalk around the west side of the pond in lieu of the trail alignment along the east side of the pond. Parks Director and Board agree to allow future 10’-12’ paved path around the west side of the Sakai pond.

Show All Answers

1. March 2014 - Hearing Examiner Decision
2. Summer 2015 - Based on Comprehensive Plan Discussions,
3. Fall 2015 - PW Staff Prepares Conceptual Trail Alignment on West Side
4. 2016 - Wetland Delineation, etc.
5. Spring 2017
6. June 2017
7. Fall 2017
8. Winter 2017
9. February 2018
10. April 2018
11. Summer 2018
12. Fall 2018
13. 2019
14. 2020
15. April 2021