Fall 2015 - PW Staff Prepares Conceptual Trail Alignment on West Side

Fall 2015 PW staff prepares conceptual trail alignment for 820’ long trail on the west side. Visconsi prepares Cost Estimates comparing costs associated with designing and constructing the trail on both the east and west sides. Negotiations proceed establishing sharing of some additional site investigation costs (wetland delineation and geotechnical reports) that Visconsi had already incurred for designing a trail on the east side.

Show All Answers

1. March 2014 - Hearing Examiner Decision
2. Summer 2015 - Based on Comprehensive Plan Discussions,
3. Fall 2015 - PW Staff Prepares Conceptual Trail Alignment on West Side
4. 2016 - Wetland Delineation, etc.
5. Spring 2017
6. June 2017
7. Fall 2017
8. Winter 2017
9. February 2018
10. April 2018
11. Summer 2018
12. Fall 2018
13. 2019
14. 2020
15. April 2021