Lovell Avenue Beach Mains

Description

Based on prior investigations of the City's beachline sewer system serving the lower Lovell pump station, the longevity and long-term integrity of the system is in need of repairs and/or replacement. The City's initial design parameters of moving the line out of the tidal zone can proffer several benefits. Currently the City has contracted with a consultant to investigate and report on alternatives for the Lovell pump station sewer basin.

Activity

  • Anticipated construction - 2019/2020
  • Conceptual design - 2017
  • Design - 2018
  • Easements - 2018/2020